The track loop that forms the Farms end and the Mill Run to the mill precinct of the cane farm line has now been laid and tested.
The track is Code 250 while the points are LGB so transition pieces had to be made to connect the two track sizes together.
The sleepers have deteriorated in the sun and do not hold the gauge well on the top of the loop so wooden spacers cut to hold the gauge have been used, they can be seen in the second picture.
The points allow a train to push through them to set the direction.
The way it is set in the first picture allows a train to run clockwise around the loop, when it returns to the point it pushes through and the train runs down to the mill.
The next train that comes from the mill runs around the loop in an anticlockwise direction and pushes through on the way back to the mill.
The points are now left set for the next train to again run clockwise and so on.
Farms loop entry/exit points |
Loop looking towards points |
Frangipani inside loop |
Loop looking away from points |
The track has been laid to the edge of the mill precinct which is the next area to be built.
The entry/exit points are Aristocraft that operate in the same way as the farm loop points.
Run to the mill looking from loop points |
Run to the farm looking from mill points |
Mill loop entry/exit points |
Once the mill end is complete there will be a dogbone style track with some sidings for shunting operations at the mill.