I divided the construction of the railway into 6
separate stages.
Stage 1; runs across the "Back Fence" of the
garden around the "Corner" (via a couple of trestle bridges) then
down the "Side Fence" (which runs the full length of the house block,
but only a small part is used). This
involved bringing the "Upper Level" track down to the same level as
the "Lower Level" where they cross a lift up bridge.
Stage 2; takes the two tracks across the yard on a
"table" which is all flat so that structures and sidings can be built
on it. A lift up
bridge, spans a gap left to allow access to the inside of the loop.
Stage 3; involved extending "the table" and
putting in benchwork across the front of the shed to carry the lower loop after
it runs through a "town area" to close it.
Stage 4; takes the track that came down in Stage 1 back up
to "Upper Level". There is a smaller area to achieve this when
compared to the "Corner" with the high trestle across it, a
Spiral/Helix was considered but eventually one was not required to achieve
this.
Stage 5; was planned to be tracks running to storage tracks under the HO layout and space for a sugar mill precinct. Due to the size of the sugar mill precinct it has now evolved into a second stand alone layout with interchange tracks to the main layout; its progress will be recorded under its own Construction Logs page (link below).
Stage 6; the planned loops running into the shed from Stage 5 with storage tracks under the HO layout, has now been abandoned This stage has now evolved into the "Re-Configuration" whose progress is recorded separately under its own Re-Configuration Construction Logs page linked below.
Note this is a work in progress at this point in time
Stage 1
1. Stage 1- August - October 2019 G The Beginning of the Railway
2. Stage 1-October to November 2019 Supports Construction
3. Stage 1-November to December 2019 Lower Level Around the Corner
4. Stage 1-January 2020 Starting the High Trestle
5. Stage 1-January 2020 The High Trestle Reaches Halfway
6. Stage 1-January 2020 The High Trestle is Finished
7. Stage 1-March 2020 Down Hill from The High Trestle
8. Stage 1-March 2020 The Low Trestle
9. Stage 1-April 2020 A walkway and safety rail is fitted to the high Trestle
10. Stage 1-April 2020 Stage 1 is Complete
Stage 2
1. Stage 2-May 2020 Stage 2 begins with Coleus Corner
2. Stage 2-May 2020 Inside the Loop Landscaping started
3. Stage 2-May 2020 Lattice Fence extended across the yard from Coleus Corner.
4. Stage 2- May 2020 Lift Up Bridge Work Begins
5. Stage 2- May 2020 The Lift Up Bridge is Redesigned
6. Stage 2- May 2020 The Lift Up Bridge is Redesigned Again
7. Stage 2- June 2020 The Lift Up Bridge Rail Decks are Built
8. Stage 2-June 2020 Baseboards Across the Yard completed
9. Stage 2- June 2020 Lift Up Bridge Finished; Stage 2 is Complete
Stage 3
1. Stage 3- June 2020 Stage 3 is Commenced
2. Stage 3-June 2020 Stage 3 Base Framework Built
3. Stage 3-July 2020 Framework is Complete
4. Stage 3-July 2020 Lower Loop Baseboards are Installed
5. Stage 3-July 2020 Lower Loop Baseboards Finished; Stage 3 is complete
Stage 4
1. Stage 4-July 2020 Lower Loop is now Continuous
1 comment:
Looks like you are really moving along with the construction. It looks neat and durable. Looking forward to that moment when the first train runs round the full circuit. 😏
Rik
Post a Comment